Weekly Update – Reconstructing King Street
Road resurfacing on King Street – The final paving of King Street is expected to be complete Thursday and Friday (weather permitting). Pavement markings will be completed Monday morning and the road will be reopened afterwards.
Storm water planters – Planting will be completed next week and the granite cladding and additional lighting features on the planers will be installed afterwards.
Stage 1 – King Street from Gaukel to Ontario
Stage 2 – King Street from Ontario to Queen
Stage 3 – King Street from Queen to Frederick
Application of sealant – The sealant will be applied to block 3 after Oktoberfest. Therefore, there will be no on street parking within this block until the sealant is applied.
Speakers Corner & Hall’s Lane
Pedestrian walkways and access
Waste disposal - The waste containers that have been used throughout construction (see locations below) will be removed by the end of next week, October 2nd.
King Street construction contact phone numbers:
City of Kitchener – Eric Saunderson, 519-741-2304 or eric.saunderson@kitchener.ca
Consultant - IBI Group – Kelly Cobbe, 519-585-2255 x225 or kcobbe@ibigroup.com
Construction Site Office – 156 King Street West, beside the Artery Gallery.
City of Kitchener Contact Centre – 519-741-2286 (after hour issues)
For details about this project, please visit: www.downtownkitchener.ca